Generally, the best thing to do is to add the costs together and to leave a note explaining the separate charges. Unfortunately, Project 2016 will only assign one fixed cost to a single task. In some instances, there might be more than one fixed cost associated with a task. How to Assign Multiple Fixed Costs in Microsoft Project?

In this case, we will want to add this to the cost of the task. Let’s say that part of the team will spend a couple of hours Connecting to Services. Note that when you sign a fixed cost to a task, you are still able to assign other costs. For now, you can set the Fixed Cost Accrual to Start – we will examine this more in the next section. In our example, we will enter a cost of Connecting Services. Today, we are just going to focus on the first few. Start by switching from the Entry Table to the Cost Table.īy default, the Cost Table contains a Fixed Cost column, a Fixed Cost Accrual column, Total Cost, Baseline Cost, Variance, Actual, and Remaining. The way that you would start to enter a fixed cost is with the Cost Table. How to Assign a Fixed Cost to a Task in Microsoft Project?


Note: This tutorial on how to assign a fixed cost to a task in Microsoft Project is suitable for all MS Project versions including Office 365 Home > Microsoft Project > How to Assign a Fixed Cost to a Task in Microsoft Project 2016? How to Assign a Fixed Cost to a Task in Microsoft Project 2016? Power Pivot, Power Query and DAX in Excel.